The cable car route connecting relics in Lac Thuy district, Hoa Binh province and Huong Son commune, My Duc district, Hanoi, is expected to be nearly 3km long.
On March 16, Deputy Prime Minister Le Van Thanh signed a decision approving the investment policy of Huong Binh cable car project in Phu Nghia commune, Lac Thuy district, Hoa Binh province and Huong Son commune, My Duc district, Ho Chi Minh City. Hanoi.
Accordingly, the cable car route named Huong Binh is designed with a length of about 2,965km; of which in Hoa Binh province is 1,486 km long and in Hanoi city 1,479 km long.
The total land use area of the project (both Hoa Binh and Hanoi ends) is 35.05ha. In which, in Hoa Binh province, the land use area is about 17.19 ha; including main items: Dynamic station; hotels, resort villas, restaurants, marinas, main entrance gates, service huts.
In Hanoi city, the land use area is about 17.86 ha; including main items: Main station and functions (administrative office area, ticket counter, medical room, souvenir shop); technical area – cable car operation …
The total investment capital of the project (including site clearance costs) is over 1,700 billion VND, invested by a private company. The project is expected to start construction this year and be completed in the fourth quarter of 2024.
Currently, at the special national relic site of Huong Pagoda, there is a 1.2km-long cable car system, with 45 cabins and 7 pillars, transporting about 1,500 passengers to visit the monument/hour, with a ticket price of about 120,000 VND/turn.
Source: CafeF.vn